Carrington
- Connection date
- 31 Oct 2027 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 20 Jul 2023
Trafford, reference 110320/FUL/23 · Source: REPD - Technology
- Storage
- Total capacity
- 680 MW
- Connected now
- 0 MW
- Still to connect
- 680 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000276
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 22 May 2026 registerConnection date moved from 30 Oct 2026 to 31 Oct 2027 (+12 months)
- 22 May 2026 registerTechnology changed from Gas (CCGT) to Storage
- 21 Nov 2025 registerRestructured from 2 stages (1,040 MW from 30 Oct 2025, 1,040 MW from 30 Oct 2036) to 1 stage (680 MW from 30 Oct 2026). First connection date +12 months
- 29 Apr 2025 registerRenamed from Trafford Power
- 29 Apr 2025 registerCustomer changed from WAINSTONES ENERGY LIMITED to Carrington Storage Limited
- 30 Jun 2023 registerRestructured from 1 stage (2,050 MW from 15 Jul 2020) to 2 stages (1,040 MW from 30 Oct 2025, 1,040 MW from 30 Oct 2036). First connection date +63 months
- 23 Dec 2022 registerSubstation name updated in the register (from Carrington 400kV to Carrington 400KV Substation)
Also at Carrington 400KV Substation
Substation view2 other projects, 2.1 GW still to connect at this substation in total. 49.9 MW is due to connect here before this project’s connection date of 31 Oct 2027.