Cryogenic Battery System (Synchronous)
- Connection date
- 8 Nov 2026
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Technology
- Storage + Reactive compensation
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000549
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 0 | 0 | 8 May 2026 | Not stated | Under Construction/Commissioning |
| 2 | 0 | 49.9 | 49.9 | 8 Nov 2026 | Not stated | Under Construction/Commissioning |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Nov 2025 registerStage 1: Status changed from Consents Approved to Under Construction/Commissioning
- 21 Nov 2025 registerStage 2: Status changed from Consents Approved to Under Construction/Commissioning
- 27 Jun 2025 registerRestructured from 1 stage (49.9 MW from 31 Oct 2024) to 2 stages (0 MW from 8 May 2026, 49.9 MW from 8 Nov 2026). First connection date +24 months
- 31 Jan 2023 registerTechnology changed from Storage to Storage, Reactive compensation
- 29 Nov 2022 registerConnection date moved from 26 Aug 2023 to 31 Oct 2024 (+14 months)
- 31 May 2022 registerStatus changed from Awaiting Consents to Consents Approved
Also at Carrington 400KV Substation
Substation view2 other projects, 2.1 GW still to connect at this substation in total.