Projects / Substation
Cairnford GSP
North Scotland, SSEN Transmission
3projects in the register
146 MWstill to connect
63 MWof that with Gate 2 offers
0 MWconnected now
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Clashindarroch 2 | VATTENFALL WIND POWER LTD | Onshore wind | 63 | 4 Jun 2027 | Gate 2 | Under construction |
| Cairnborrow Wind Energy Hub | BPUWL 29 LIMITED | Storage with solar or wind | 43.2 | 31 Oct 2031 | Gate 1 | Scoping |
| Tarbuckle Hill Wind Farm | ENERGIEKONTOR UK LTD | Onshore wind | 39.6 | 31 Oct 2031 | Not stated | Scoping |
Recent changes
- Clashindarroch 2North Scotland, Onshore windStatus changed from Scoping to Under construction
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose