Clashindarroch 2
- Connection date
- 4 Jun 2027 +9 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Planning consent
- Granted on appeal 26 Jun 2023
Scottish Government (S36), reference ECU00002002 · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Onshore wind
- Total capacity
- 63 MW
- Connected now
- 0 MW
- Still to connect
- 63 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Embedded
- Region
- North Scotland
- Project number
- PRO-000041
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 14 Jul 2026 registerRestructured from 1 stage (77 MW from 31 Aug 2026) to 1 stage (63 MW from 4 Jun 2027). First connection date +9 months
- 26 Apr 2024 registerConnection date moved from 30 Apr 2025 to 31 Aug 2026 (+16 months)
- 26 Apr 2024 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 30 Nov 2021 registerSubstation name updated in the register (from Cairnford to Cairnford GSP)
- 30 Mar 2021 registerConnection date moved from 30 Apr 2024 to 30 Apr 2025 (+12 months)
Also at Cairnford GSP
Substation view2 other projects, 146 MW still to connect at this substation in total.