Burwell 400kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Burwell GEC (Ethos Green) | BURWELL GREEN ENERGY CENTRE LTD | Storage with solar or wind | 480 | 31 Oct 2032 | Gate 1 | Scoping |
| Breach Solar Farm | Burwell 11 Solar Limited | Storage with solar or wind | 0 | Connected | Not stated | Built |
Recent changes
- Burwell GEC (Ethos Green)England and Wales, Storage with solar or windMarked as Gate 1
- Breach Solar FarmEngland and Wales, Storage with solar or wind49.9 MW now connectedConnected
- Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
- Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Built
- Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 24 Nov 2023 to 25 Apr 2024 (+5 months)+5 mo
- Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Under Construction/Commissioning to Consents Approved
- Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell Main 400kV Substation to Burwell 400kV Substation
- Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 12 May 2023 to 24 Nov 2023 (+6 months)+6 mo
- Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Under Construction/Commissioning
- Burwell GEC (Ethos Green)England and Wales, Storage with solar or windRenamed from Burwell GEC
- Burwell GEC (Ethos Green)England and Wales, Storage with solar or windAdded to the registerNew
- Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Burwell II (Waterbeach) Solar
- Breach Solar FarmEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
- Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Waterbeach Solar Farm
- Breach Solar FarmEngland and Wales, Storage with solar or windCustomer changed from Waterbeach Solar Limited to BURWELL 11 SOLAR LIMITED
- Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
- Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
- Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2022 to 12 May 2023 (+10 months)+10 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?