Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Burwell 400kV Substation

England and Wales, National Grid Electricity Transmission

2projects in the register
480 MWstill to connect
0 MWof that with Gate 2 offers
49.9 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Burwell GEC (Ethos Green)BURWELL GREEN ENERGY CENTRE LTDStorage with solar or wind48031 Oct 2032Gate 1Scoping
Breach Solar FarmBurwell 11 Solar LimitedStorage with solar or wind0ConnectedNot statedBuilt

Recent changes

  • Burwell GEC (Ethos Green)England and Wales, Storage with solar or windMarked as Gate 1
  • Breach Solar FarmEngland and Wales, Storage with solar or wind49.9 MW now connectedConnected
  • Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Built
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 24 Nov 2023 to 25 Apr 2024 (+5 months)+5 mo
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Under Construction/Commissioning to Consents Approved
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell Main 400kV Substation to Burwell 400kV Substation
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 12 May 2023 to 24 Nov 2023 (+6 months)+6 mo
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Under Construction/Commissioning
  • Burwell GEC (Ethos Green)England and Wales, Storage with solar or windRenamed from Burwell GEC
  • Burwell GEC (Ethos Green)England and Wales, Storage with solar or windAdded to the registerNew
  • Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Burwell II (Waterbeach) Solar
  • Breach Solar FarmEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
  • Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Waterbeach Solar Farm
  • Breach Solar FarmEngland and Wales, Storage with solar or windCustomer changed from Waterbeach Solar Limited to BURWELL 11 SOLAR LIMITED
  • Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2022 to 12 May 2023 (+10 months)+10 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO