Breach Solar Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Storage + Solar
- Total capacity
- 49.9 MW
- Connected now
- 49.9 MW
- Still to connect
- 0 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001019
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Aug 2025 register49.9 MW now connected
- 29 Aug 2025 registerCapacity changed from 50 MW to 49.9 MW
- 29 Aug 2025 registerStatus changed from Consents Approved to Built
- 26 Apr 2024 registerConnection date moved from 24 Nov 2023 to 25 Apr 2024 (+5 months)
- 26 Apr 2024 registerStatus changed from Under Construction/Commissioning to Consents Approved
- 29 Dec 2023 registerConnection point changed from Burwell Main 400kV Substation to Burwell 400kV Substation
- 29 Dec 2023 registerConnection date moved from 12 May 2023 to 24 Nov 2023 (+6 months)
- 29 Dec 2023 registerStatus changed from Awaiting Consents to Under Construction/Commissioning
- 28 Apr 2023 registerRenamed from Burwell II (Waterbeach) Solar
- 28 Apr 2023 registerTechnology changed from Solar to Storage, Solar
- 23 Dec 2022 registerConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
- 28 Jan 2022 registerRenamed from Waterbeach Solar Farm
- 28 Jan 2022 registerCustomer changed from Waterbeach Solar Limited to BURWELL 11 SOLAR LIMITED
- 28 Jan 2022 registerCapacity changed from 50 MW to 50 MW
- 28 Jan 2022 registerStatus changed from Scoping to Awaiting Consents
- 31 Dec 2021 registerConnection date moved from 30 Jun 2022 to 12 May 2023 (+10 months)
Also at Burwell 400kV Substation
Substation view1 other project, 480 MW still to connect at this substation in total.