Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Burwell 11 Solar Limited

Customer named in the TEC register

1project in the register
0 MWstill to connect
0 MWof that with Gate 2 offers
49.9 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Breach Solar FarmBurwell 400kV SubstationStorage with solar or wind0ConnectedNot statedBuilt

Left the register since January 2021: Burwell II (Waterbeach) Solar (50 MW).

Recent changes

  • Breach Solar FarmEngland and Wales, Storage with solar or wind49.9 MW now connectedConnected
  • Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 49.9 MW
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Consents Approved to Built
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 24 Nov 2023 to 25 Apr 2024 (+5 months)+5 mo
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Under Construction/Commissioning to Consents Approved
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell Main 400kV Substation to Burwell 400kV Substation
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 12 May 2023 to 24 Nov 2023 (+6 months)+6 mo
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Awaiting Consents to Under Construction/Commissioning
  • Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Burwell II (Waterbeach) Solar
  • Breach Solar FarmEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Burwell 400kV to Burwell Main 400kV Substation
  • Breach Solar FarmEngland and Wales, Storage with solar or windRenamed from Waterbeach Solar Farm
  • Breach Solar FarmEngland and Wales, Storage with solar or windCustomer changed from Waterbeach Solar Limited to BURWELL 11 SOLAR LIMITED
  • Breach Solar FarmEngland and Wales, Storage with solar or windCapacity changed from 50 MW to 50 MW
  • Breach Solar FarmEngland and Wales, Storage with solar or windStatus changed from Scoping to Awaiting Consents
  • Burwell II (Waterbeach) SolarEngland and Wales, SolarLeft the register (50 MW from 21 Oct 2022)50 MW
  • Breach Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2022 to 12 May 2023 (+10 months)+10 mo
  • Burwell II (Waterbeach) SolarEngland and Wales, SolarAdded to the registerNew
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO