Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Axminster 132kV Substation

England and Wales, National Grid Electricity Transmission

4projects in the register
590 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
AxminsterHB825AXM LTDStorage12031 Oct 2024 Past dateGate 1Awaiting Consents
Axminster BESSCSE25 LIMITEDStorage15031 Oct 2028Gate 1Scoping
Axminster - New ConnectionENSO GREEN HOLDINGS B LIMITEDStorage12030 Jun 2029Gate 1Scoping
Old Park FarmSTARLIGHT ENERGY UK LIMITEDStorage with solar or wind20023 Jun 2038 −4 moGate 1Scoping

Recent changes

  • Old Park FarmEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2038 to 23 Jun 2038 (−4 months)−4 mo
  • Old Park FarmEngland and Wales, Storage with solar or windMarked as Gate 1
  • AxminsterEngland and Wales, StorageMarked as Gate 1
  • AxminsterEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
  • Axminster BESSEngland and Wales, StorageMarked as Gate 1
  • Axminster BESSEngland and Wales, StorageRenamed from Axminster
  • Axminster - New ConnectionEngland and Wales, StorageMarked as Gate 1
  • Axminster BESSEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
  • Axminster - New ConnectionEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
  • Axminster - New ConnectionEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
  • Axminster - New ConnectionEngland and Wales, StorageRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (120 MW from 30 Jun 2029). First connection date +48 months+48 mo
  • Old Park FarmEngland and Wales, Storage with solar or windAdded to the registerNew
  • AxminsterEngland and Wales, StorageRenamed from Axminster Tertiary
  • AxminsterEngland and Wales, StorageStatus changed from Scoping to Awaiting Consents
  • Axminster BESSEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
  • Axminster BESSEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster
  • AxminsterEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
  • Axminster - New ConnectionEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
  • Axminster BESSEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
  • Axminster BESSEngland and Wales, StorageAdded to the registerNew
  • AxminsterEngland and Wales, StorageCapacity changed from 49.9 MW to 120 MW
  • AxminsterEngland and Wales, StorageConnection date moved from 1 Oct 2022 to 31 Oct 2024 (+25 months)+25 mo
  • AxminsterEngland and Wales, StorageConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)+9 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO