Axminster 132kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Axminster | HB825AXM LTD | Storage | 120 | 31 Oct 2024 Past date | Gate 1 | Awaiting Consents |
| Axminster BESS | CSE25 LIMITED | Storage | 150 | 31 Oct 2028 | Gate 1 | Scoping |
| Axminster - New Connection | ENSO GREEN HOLDINGS B LIMITED | Storage | 120 | 30 Jun 2029 | Gate 1 | Scoping |
| Old Park Farm | STARLIGHT ENERGY UK LIMITED | Storage with solar or wind | 200 | 23 Jun 2038 −4 mo | Gate 1 | Scoping |
Recent changes
- Old Park FarmEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2038 to 23 Jun 2038 (−4 months)−4 mo
- Old Park FarmEngland and Wales, Storage with solar or windMarked as Gate 1
- AxminsterEngland and Wales, StorageMarked as Gate 1
- AxminsterEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
- Axminster BESSEngland and Wales, StorageMarked as Gate 1
- Axminster BESSEngland and Wales, StorageRenamed from Axminster
- Axminster - New ConnectionEngland and Wales, StorageMarked as Gate 1
- Axminster BESSEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
- Axminster - New ConnectionEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
- Axminster - New ConnectionEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- Axminster - New ConnectionEngland and Wales, StorageRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (120 MW from 30 Jun 2029). First connection date +48 months+48 mo
- Old Park FarmEngland and Wales, Storage with solar or windAdded to the registerNew
- AxminsterEngland and Wales, StorageRenamed from Axminster Tertiary
- AxminsterEngland and Wales, StorageStatus changed from Scoping to Awaiting Consents
- Axminster BESSEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
- Axminster BESSEngland and Wales, StorageConnection point changed from Axminster 400kV Substation to Axminster
- AxminsterEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
- Axminster - New ConnectionEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
- Axminster BESSEngland and Wales, StorageConnection point changed from Axminster to Axminster 400kV Substation
- Axminster BESSEngland and Wales, StorageAdded to the registerNew
- AxminsterEngland and Wales, StorageCapacity changed from 49.9 MW to 120 MW
- AxminsterEngland and Wales, StorageConnection date moved from 1 Oct 2022 to 31 Oct 2024 (+25 months)+25 mo
- AxminsterEngland and Wales, StorageConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose