Axminster
- Connection date
- 31 Oct 2024
- Gate
- Gate 1
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001017
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 5 Jun 2026 registerMarked as Gate 1
- 12 May 2026 registerConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
- 30 May 2023 registerRenamed from Axminster Tertiary
- 28 Feb 2023 registerStatus changed from Scoping to Awaiting Consents
- 30 Mar 2022 registerConnection point changed from Axminster to Axminster 400kV Substation
- 29 Oct 2021 registerCapacity changed from 49.9 MW to 120 MW
- 29 Oct 2021 registerConnection date moved from 1 Oct 2022 to 31 Oct 2024 (+25 months)
- 26 Feb 2021 registerConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)
Also at Axminster 132kV Substation
Substation view3 other projects, 590 MW still to connect at this substation in total.