Axminster - New Connection
- Connection date
- 30 Jun 2029
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001356
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 9 Dec 2025 registerMarked as Gate 1
- 29 Oct 2024 registerConnection point changed from Axminster 400kV Substation to Axminster 132kV Substation
- 29 Oct 2024 registerTechnology changed from Storage, Solar to Storage
- 27 Sep 2024 registerRestructured from 3 stages (49.9 MW from 30 Jun 2025, 49.9 MW from 30 Jun 2026, 20.2 MW from 30 Dec 2026) to 1 stage (120 MW from 30 Jun 2029). First connection date +48 months
- 30 Mar 2022 registerConnection point changed from Axminster to Axminster 400kV Substation
Also at Axminster 132kV Substation
Substation view3 other projects, 590 MW still to connect at this substation in total. 270 MW is due to connect here before this project’s connection date of 30 Jun 2029.