Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

Aberthaw 275kV Substation

England and Wales, National Grid Electricity Transmission

5projects in the register
1 GWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Aberthaw EnergyABERTHAW ENERGY LIMITEDStorage24930 Oct 2028Gate 1Scoping
Aberthaw (Tertiary)Aberthaw Green LimitedStorage with solar or wind5731 Oct 2029Gate 1Scoping
Aberthaw PV & BESS GenerationREWE 12 LimitedStorage20031 Oct 2029 +4 moGate 1Scoping
Afon DdawLIGHTSOURCE SPV 214 LIMITEDStorage with solar or wind24931 Oct 2029Not statedScoping
Mwyndy StorageCENIN RENEWABLES LIMITEDStorage24930 Oct 2037Gate 1Scoping

Left the register since January 2021: Aberthaw (0 MW).

Recent changes

  • Aberthaw PV & BESS GenerationEngland and Wales, StorageConnection date moved from 30 Jun 2029 to 31 Oct 2029 (+4 months)+4 mo
  • Aberthaw PV & BESS GenerationEngland and Wales, StorageMarked as Gate 1
  • Mwyndy StorageEngland and Wales, StorageMarked as Gate 1
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
  • Aberthaw EnergyEngland and Wales, StorageMarked as Gate 1
  • Aberthaw PV & BESS GenerationEngland and Wales, StorageCustomer changed from CYP SOLAR LIMITED to REWE 12 Limited
  • Afon DdawEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2033)
  • Afon DdawEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2028 to 31 Oct 2029 (+12 months)+12 mo
  • Afon DdawEngland and Wales, Storage with solar or windNew stage added (0 MW from 31 Oct 2033)
  • Mwyndy StorageEngland and Wales, StorageAdded to the registerNew
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 31 Oct 2029 (+60 months)+60 mo
  • Aberthaw PV & BESS GenerationEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
  • Afon DdawEngland and Wales, Storage with solar or windRenamed from Morgannwg Solar Farm
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to Aberthaw Green Limited
  • AberthawEngland and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windTechnology changed from Hybrid to Storage, Solar
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 1 Oct 2024 to 31 Oct 2024 (+1 month)+1 mo
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 1 Oct 2024 (−1 month)−1 mo
  • Aberthaw PV & BESS GenerationEngland and Wales, StorageAdded to the registerNew
  • Afon DdawEngland and Wales, Storage with solar or windAdded to the registerNew
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windTechnology changed from Storage, Solar to Hybrid
  • Aberthaw EnergyEngland and Wales, StorageSubstation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
  • AberthawEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2026 to 31 Oct 2024 (−24 months)−24 mo
  • Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 31 Oct 2026 (+24 months)+24 mo
  • Aberthaw EnergyEngland and Wales, StorageAdded to the registerNew
  • AberthawEngland and Wales, Thermal (gas, biomass, waste)50 MW no longer connected
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO