Aberthaw 275kV Substation
England and Wales, National Grid Electricity Transmission
The queue at this substation
| Project | Customer | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Aberthaw Energy | ABERTHAW ENERGY LIMITED | Storage | 249 | 30 Oct 2028 | Gate 1 | Scoping |
| Aberthaw (Tertiary) | Aberthaw Green Limited | Storage with solar or wind | 57 | 31 Oct 2029 | Gate 1 | Scoping |
| Aberthaw PV & BESS Generation | REWE 12 Limited | Storage | 200 | 31 Oct 2029 +4 mo | Gate 1 | Scoping |
| Afon Ddaw | LIGHTSOURCE SPV 214 LIMITED | Storage with solar or wind | 249 | 31 Oct 2029 | Not stated | Scoping |
| Mwyndy Storage | CENIN RENEWABLES LIMITED | Storage | 249 | 30 Oct 2037 | Gate 1 | Scoping |
Left the register since January 2021: Aberthaw (0 MW).
Recent changes
- Aberthaw PV & BESS GenerationEngland and Wales, StorageConnection date moved from 30 Jun 2029 to 31 Oct 2029 (+4 months)+4 mo
- Aberthaw PV & BESS GenerationEngland and Wales, StorageMarked as Gate 1
- Mwyndy StorageEngland and Wales, StorageMarked as Gate 1
- Aberthaw (Tertiary)England and Wales, Storage with solar or windMarked as Gate 1
- Aberthaw EnergyEngland and Wales, StorageMarked as Gate 1
- Aberthaw PV & BESS GenerationEngland and Wales, StorageCustomer changed from CYP SOLAR LIMITED to REWE 12 Limited
- Afon DdawEngland and Wales, Storage with solar or windStage removed (0 MW from 31 Oct 2033)
- Afon DdawEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2028 to 31 Oct 2029 (+12 months)+12 mo
- Afon DdawEngland and Wales, Storage with solar or windNew stage added (0 MW from 31 Oct 2033)
- Mwyndy StorageEngland and Wales, StorageAdded to the registerNew
- Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 31 Oct 2029 (+60 months)+60 mo
- Aberthaw PV & BESS GenerationEngland and Wales, StorageTechnology changed from Storage, Solar to Storage
- Afon DdawEngland and Wales, Storage with solar or windRenamed from Morgannwg Solar Farm
- Aberthaw (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to Aberthaw Green Limited
- AberthawEngland and Wales, Thermal (gas, biomass, waste)Left the register (0 MW)0 MW
- Aberthaw (Tertiary)England and Wales, Storage with solar or windTechnology changed from Hybrid to Storage, Solar
- Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 1 Oct 2024 to 31 Oct 2024 (+1 month)+1 mo
- Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 1 Oct 2024 (−1 month)−1 mo
- Aberthaw PV & BESS GenerationEngland and Wales, StorageAdded to the registerNew
- Afon DdawEngland and Wales, Storage with solar or windAdded to the registerNew
- Aberthaw (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
- Aberthaw (Tertiary)England and Wales, Storage with solar or windTechnology changed from Storage, Solar to Hybrid
- Aberthaw EnergyEngland and Wales, StorageSubstation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
- AberthawEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
- Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2026 to 31 Oct 2024 (−24 months)−24 mo
- Aberthaw (Tertiary)England and Wales, Storage with solar or windConnection date moved from 31 Oct 2024 to 31 Oct 2026 (+24 months)+24 mo
- Aberthaw EnergyEngland and Wales, StorageAdded to the registerNew
- AberthawEngland and Wales, Thermal (gas, biomass, waste)50 MW no longer connected
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose