Aberthaw PV & BESS Generation
- Connection date
- 31 Oct 2029 +4 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001815
- In the register since
- May 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 30 Jun 2029 to 31 Oct 2029 (+4 months)
- 10 Oct 2026 registerMarked as Gate 1
- 15 May 2026 registerCustomer changed from CYP SOLAR LIMITED to REWE 12 Limited
- 31 Jan 2025 registerTechnology changed from Storage, Solar to Storage
- 31 May 2022 registerAdded to the register
Also at Aberthaw 275kV Substation
Substation view4 other projects, 1 GW still to connect at this substation in total. 249 MW is due to connect here before this project’s connection date of 31 Oct 2029.
- Aberthaw EnergyABERTHAW ENERGY LIMITED, Storage, Gate 1Oct 2028249 MW
- Aberthaw (Tertiary)Aberthaw Green Limited, Storage with solar or wind, Gate 1Oct 202957 MW
- Afon DdawLIGHTSOURCE SPV 214 LIMITED, Storage with solar or wind, Not statedOct 2029249 MW
- Mwyndy StorageCENIN RENEWABLES LIMITED, Storage, Gate 1Oct 2037249 MW