Aberthaw Energy
- Connection date
- 30 Oct 2028
- Gate
- Gate 1
- Status
- Scoping
- Planning consent
- Application submitted 16 Dec 2025
Vale of Glamorgan, reference 2025/01282/FUL · Source: REPD - Technology
- Storage
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001697
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 May 2026 registerMarked as Gate 1
- 30 Mar 2022 registerSubstation name updated in the register (from Aberthaw 275kV to Aberthaw 275kV Substation)
- 31 Dec 2021 registerAdded to the register
Also at Aberthaw 275kV Substation
Substation view4 other projects, 1 GW still to connect at this substation in total.
- Aberthaw (Tertiary)Aberthaw Green Limited, Storage with solar or wind, Gate 1Oct 202957 MW
- Aberthaw PV & BESS GenerationREWE 12 Limited, Storage, Gate 1Oct 2029200 MW
- Afon DdawLIGHTSOURCE SPV 214 LIMITED, Storage with solar or wind, Not statedOct 2029249 MW
- Mwyndy StorageCENIN RENEWABLES LIMITED, Storage, Gate 1Oct 2037249 MW