Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / Substation

132kV bay at Iron Acton Substation

England and Wales, National Grid Electricity Transmission

1project in the register
20.6 MWstill to connect
20.6 MWof that with Gate 2 offers
99.4 MWconnected now

The queue at this substation

ProjectCustomerTechnologyQueued MWConnection dateGateStatus
Iron ActonIRON ACTON GREEN LIMITEDStorage with solar or wind20.630 Sep 2026 Past dateGate 2Consents Approved

Recent changes

  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Status changed from Under Construction/Commissioning to Consents Approved
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Given a Gate 2 connection offerGate 2
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Under Construction/Commissioning
  • Iron ActonEngland and Wales, Storage with solar or windConnection point changed from Iron Acton - (South West) GSP to 132kV bay at Iron Acton Substation
  • Iron ActonEngland and Wales, Storage with solar or windConnection point changed from Iron Acton 275kV Substation to Iron Acton - (South West) GSP
  • Iron ActonEngland and Wales, Storage with solar or windConnection date moved from 30 Sep 2027 to 30 Sep 2026 (−12 months)−12 mo
  • Iron ActonEngland and Wales, Storage with solar or windConnected MW moved between stages in the register (99.4 MW connected, unchanged)
  • Iron ActonEngland and Wales, Storage with solar or windStage removed (49.5 MW connected)
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: 49.5 MW now connectedConnected
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Status changed from Scoping to Built
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Capacity changed from 49.9 MW to 49.5 MW
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Connection date moved from 31 Jul 2023 to 30 Sep 2024 (+14 months)+14 mo
  • Iron ActonEngland and Wales, Storage with solar or windStage 3: Capacity changed from 20.2 MW to 20.6 MW
  • Iron ActonEngland and Wales, Storage with solar or windStage 3: Connection date moved from 31 Oct 2023 to 30 Sep 2027 (+47 months)+47 mo
  • Iron ActonEngland and Wales, Storage with solar or windStage 1: 49.9 MW now connectedConnected
  • Iron ActonEngland and Wales, Storage with solar or windStage 1: Connection date removed (was 31 Jul 2022)
  • Iron ActonEngland and Wales, Storage with solar or windStage 1: Status changed from Scoping to Built
  • Iron ActonEngland and Wales, Storage with solar or windStage 1: Technology changed from Hybrid to Storage, Solar
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Technology changed from Hybrid to Storage, Solar
  • Iron ActonEngland and Wales, Storage with solar or windStage 3: Technology changed from Hybrid to Storage, Solar
  • Iron ActonEngland and Wales, Storage with solar or windSubstation name updated in the register (from Iron Acton GSP to Iron Acton 275kV Substation)
  • Iron ActonEngland and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Hybrid
  • Iron ActonEngland and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Hybrid
  • Iron ActonEngland and Wales, Storage with solar or windStage 3: Technology changed from Storage, Solar to Hybrid
  • Iron ActonEngland and Wales, Storage with solar or windSubstation name updated in the register (from Iron Acton to Iron Acton GSP)
  • Iron ActonEngland and Wales, Storage with solar or windRestructured from 1 stage (120 MW from 30 Nov 2021) to 3 stages (49.9 MW from 31 Jul 2022, 49.9 MW from 31 Jul 2023, 20.2 MW from 31 Oct 2023). First connection date +8 months+8 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO