QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Projects / England and Wales
Connection date
30 Sep 2026
Gate
Not stated
Status
Under construction
Technology
Storage + Solar
Total capacity
120 MW
Connected now
99.4 MW
Still to connect
20.6 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000491
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
199.4099.4NoneNot statedBuilt
2020.612030 Sep 2026Not statedUnder construction

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at 132kV bay at Iron Acton Substation

Substation view

No other projects in the register at this connection point.