- Connection date
- 30 Sep 2026
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 120 MW
- Connected now
- 99.4 MW
- Still to connect
- 20.6 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000491
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 99.4 | 0 | 99.4 | None | Not stated | Built |
| 2 | 0 | 20.6 | 120 | 30 Sep 2026 | Gate 2 | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 5 Oct 2026 registerStage 2: Status changed from Under Construction/Commissioning to Consents Approved
- 5 Oct 2026 registerStage 2: Given a Gate 2 connection offer
- 7 Aug 2026 registerStage 2: Status changed from Scoping to Under Construction/Commissioning
- 29 Aug 2025 registerConnection point changed from Iron Acton - (South West) GSP to 132kV bay at Iron Acton Substation
- 27 Jun 2025 registerConnection point changed from Iron Acton 275kV Substation to Iron Acton - (South West) GSP
- 27 Jun 2025 registerConnection date moved from 30 Sep 2027 to 30 Sep 2026 (−12 months)
- 27 Jun 2025 registerConnected MW moved between stages in the register (99.4 MW connected, unchanged)
- 27 Jun 2025 registerStage removed (49.5 MW connected)
- 29 Apr 2025 registerStage 2: 49.5 MW now connected
- 29 Apr 2025 registerStage 2: Status changed from Scoping to Built
- 31 Oct 2023 registerStage 2: Capacity changed from 49.9 MW to 49.5 MW
- 31 Oct 2023 registerStage 2: Connection date moved from 31 Jul 2023 to 30 Sep 2024 (+14 months)
- 31 Oct 2023 registerStage 3: Capacity changed from 20.2 MW to 20.6 MW
- 31 Oct 2023 registerStage 3: Connection date moved from 31 Oct 2023 to 30 Sep 2027 (+47 months)
- 29 Sep 2023 registerStage 1: 49.9 MW now connected
- 29 Aug 2023 registerStage 1: Connection date removed (was 31 Jul 2022)
- 29 Aug 2023 registerStage 1: Status changed from Scoping to Built
- 29 Aug 2023 registerStage 1: Technology changed from Hybrid to Storage, Solar
- 29 Aug 2023 registerStage 2: Technology changed from Hybrid to Storage, Solar
- 29 Aug 2023 registerStage 3: Technology changed from Hybrid to Storage, Solar
- 28 Jul 2023 registerSubstation name updated in the register (from Iron Acton GSP to Iron Acton 275kV Substation)
- 30 May 2023 registerStage 1: Technology changed from Storage, Solar to Hybrid
- 30 May 2023 registerStage 2: Technology changed from Storage, Solar to Hybrid
- 30 May 2023 registerStage 3: Technology changed from Storage, Solar to Hybrid
- 23 Dec 2022 registerSubstation name updated in the register (from Iron Acton to Iron Acton GSP)
- 25 Feb 2022 registerRestructured from 1 stage (120 MW from 30 Nov 2021) to 3 stages (49.9 MW from 31 Jul 2022, 49.9 MW from 31 Jul 2023, 20.2 MW from 31 Oct 2023). First connection date +8 months
Also at 132kV bay at Iron Acton Substation
Substation viewNo other projects in the register at this connection point.