- Connection date
- 29 Oct 2033
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Application submitted 28 Nov 2022
Scottish Government (S36), reference ECU00003426 · Source: REPD - Technology
- Storage + Onshore wind
- Total capacity
- 80 MW
- Connected now
- 0 MW
- Still to connect
- 80 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004805
- In the register since
- November 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 26 Nov 2024 registerAdded to the register
Also at Teviot 400/132kV Substation
Substation view2 other projects, 808 MW still to connect at this substation in total. 523 MW is due to connect here before this project’s connection date of 29 Oct 2033.