Dounreay BESS
- Connection date
- 31 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-004749
- In the register since
- October 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Mar 2026 registerMarked as Gate 1
- 31 Jan 2025 registerConnection date moved from 31 Oct 2033 to 31 Oct 2034 (+12 months)
- 29 Oct 2024 registerAdded to the register
Also at New Dounreay 400kV substation
Substation view1 other project, 1.7 GW still to connect at this substation in total. 1.5 GW is due to connect here before this project’s connection date of 31 Oct 2034.