FIELD DEVCO LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Field Glenniston BESS | FIELD GLENNISTON BESS 132KV SUBSTATION | Storage | 200 | 29 Oct 2032 | Gate 1 | Scoping |
| Broadford BESS | Broadford 132kV Substation | Storage | 200 | 31 Oct 2034 | Gate 1 | Scoping |
| Dounreay BESS | New Dounreay 400kV substation | Storage | 200 | 31 Oct 2034 | Gate 1 | Scoping |
| Fort Augustus BESS | Fort Augustus 400kV | Storage | 200 | 31 Oct 2035 | Gate 1 | Scoping |
| Whitson BESS | Whitson 275kV Substation | Storage | 150 | 30 Oct 2037 | Gate 1 | Scoping |
Recent changes
- Field Glenniston BESSSouth Scotland, StorageTransmission owner changed from SHET to SPT
- Field Glenniston BESSSouth Scotland, StorageTransmission owner changed from SPT to SHET
- Broadford BESSNorth Scotland, StorageMarked as Gate 1
- Field Glenniston BESSSouth Scotland, StorageConnection point changed from Mossmoran 400kV Substation to FIELD GLENNISTON BESS 132KV SUBSTATION
- Field Glenniston BESSSouth Scotland, StorageMarked as Gate 1
- Fort Augustus BESSNorth Scotland, StorageMarked as Gate 1
- Whitson BESSEngland and Wales, StorageMarked as Gate 1
- Dounreay BESSNorth Scotland, StorageMarked as Gate 1
- Broadford BESSNorth Scotland, StorageConnection point changed from Broadford GSP to Broadford 132kV Substation
- Fort Augustus BESSNorth Scotland, StorageConnection point changed from Fort Augustus GSP to Fort Augustus 400kV
- Field Glenniston BESSSouth Scotland, StorageConnection point changed from Glenniston GSP to Mossmoran 400kV Substation
- Dounreay BESSNorth Scotland, StorageConnection date moved from 31 Oct 2033 to 31 Oct 2034 (+12 months)+12 mo
- Broadford BESSNorth Scotland, StorageAdded to the registerNew
- Whitson BESSEngland and Wales, StorageConnection date moved from 31 Oct 2037 to 30 Oct 2037 (1 day earlier)
- Dounreay BESSNorth Scotland, StorageAdded to the registerNew
- Field Glenniston BESSSouth Scotland, StorageAdded to the registerNew
- Whitson BESSEngland and Wales, StorageAdded to the registerNew
- Fort Augustus BESSNorth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?