Cockenzie BESS
- Connection date
- 31 Jul 2027 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Planning consent
- Granted 23 Jul 2025
Scottish Government (S36), reference ECU00006022 · Source: REPD - Technology
- Storage
- Total capacity
- 102 MW
- Connected now
- 0 MW
- Still to connect
- 102 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-004217
- In the register since
- September 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 30 Jun 2026 registerConnection point changed from Cockenzie 400/132kV to Meadowmill 400/132kV Substation
- 30 Jun 2026 registerConnection date moved from 31 Jul 2026 to 31 Jul 2027 (+12 months)
- 30 Jun 2026 registerGiven a Gate 2 connection offer
- 30 Sep 2025 registerTransmission owner changed from NGET to SPT
- 28 Mar 2025 registerCustomer changed from CANUSIA LTD to COCKENZIE STORAGE B LTD
- 28 Feb 2025 registerTransmission owner changed from SPT to NGET
- 29 Oct 2024 registerCustomer changed from ELBESS LTD to CANUSIA LTD
- 27 Sep 2024 registerSubstation name updated in the register (from Cockenzie 400/132kV Substation to Cockenzie 400/132kV)
- 27 Feb 2024 registerConnection point changed from Cockenzie 275kV Substation to Cockenzie 400/132kV Substation
- 29 Sep 2023 registerAdded to the register
Also at Meadowmill 400/132kV Substation
Substation view1 other project, 342 MW still to connect at this substation in total.