Gresham House Cockenzie BESS
COCKENZIE STORAGE LIMITED at Meadowmill 400/132kV Substation
- Connection date
- 31 Jul 2027 +12 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-002209
- In the register since
- November 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Under Construction/Commissioning
- 19 Jun 2026 registerConnection date moved from 31 Jul 2026 to 31 Jul 2027 (+12 months)
- 19 Jun 2026 registerGiven a Gate 2 connection offer
- 6 Jan 2026 registerConnection point changed from Cockenzie 400/132kV to Meadowmill 400/132kV Substation
- 29 Aug 2025 registerConnection point changed from Cockenzie 275/33kV to Cockenzie 400/132kV
- 29 Oct 2024 registerSubstation name updated in the register (from Cockenzie GSP to Cockenzie 275/33kV)
- 28 Feb 2023 registerCustomer changed from Gresham House Asset Management Limited to COCKENZIE STORAGE LIMITED
- 23 Dec 2022 registerSubstation name updated in the register (from Cockenzie to Cockenzie GSP)
- 29 Nov 2022 registerAdded to the register
Also at Meadowmill 400/132kV Substation
Substation view1 other project, 342 MW still to connect at this substation in total.