COCKENZIE STORAGE B LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Cockenzie BESS | Meadowmill 400/132kV Substation | Storage | 102 | 31 Jul 2027 +12 mo | Gate 2 | Under Construction/Commissioning |
Recent changes
- Cockenzie BESSSouth Scotland, StorageStatus changed from Scoping to Under Construction/Commissioning
- Cockenzie BESSSouth Scotland, StorageConnection point changed from Cockenzie 400/132kV to Meadowmill 400/132kV Substation
- Cockenzie BESSSouth Scotland, StorageConnection date moved from 31 Jul 2026 to 31 Jul 2027 (+12 months)+12 mo
- Cockenzie BESSSouth Scotland, StorageGiven a Gate 2 connection offerGate 2
- Cockenzie BESSSouth Scotland, StorageTransmission owner changed from NGET to SPT
- Cockenzie BESSSouth Scotland, StorageCustomer changed from CANUSIA LTD to COCKENZIE STORAGE B LTD
- Cockenzie BESSSouth Scotland, StorageTransmission owner changed from SPT to NGET
- Cockenzie BESSSouth Scotland, StorageCustomer changed from ELBESS LTD to CANUSIA LTD
- Cockenzie BESSSouth Scotland, StorageSubstation name updated in the register (from Cockenzie 400/132kV Substation to Cockenzie 400/132kV)
- Cockenzie BESSSouth Scotland, StorageConnection point changed from Cockenzie 275kV Substation to Cockenzie 400/132kV Substation
- Cockenzie BESSSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?