- Connection date
- 30 Oct 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 240 MW
- Connected now
- 0 MW
- Still to connect
- 240 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004009
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Dec 2025 registerMarked as Gate 1
- 28 Feb 2025 registerConnection point changed from Stoke Bardolph 400kV Substation to Trent Valley South Connection Node D 400kV Substation
- 28 Feb 2025 registerConnection date moved from 31 Oct 2032 to 30 Oct 2034 (+24 months)
- 26 Mar 2024 registerAdded to the register
Also at Trent Valley South Connection Node D 400kV Substation
Substation view3 other projects, 6.4 GW still to connect at this substation in total.
- Stoke BardolphStoke Bardolph 10 Renewables Limited, Storage with solar or wind, Not statedOct 20341 GW
- Bute Hydrogen Project 1HALDANE ENERGY PROJECT 1 LIMITED, Thermal (gas, biomass, waste), Gate 1Oct 20354.8 GW
- Noventum - BudbyNOVENTUM POWER SOLAR 15 LIMITED, Storage with solar or wind, Gate 1Oct 2035380 MW