- Connection date
- 31 Oct 2034
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003405
- In the register since
- August 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Sep 2024 registerConnection point changed from Stoke Bardolph 400kV Substation to Trent Valley South Connection Node D 400kV Substation
- 27 Sep 2024 registerConnection date moved from 31 Oct 2032 to 31 Oct 2034 (+24 months)
- 27 Feb 2024 registerCustomer changed from ORRÖN ENERGY DEVELOPMENT LIMITED to Stoke Bardolph 10 Renewables Limited
- 29 Aug 2023 registerAdded to the register
Also at Trent Valley South Connection Node D 400kV Substation
Substation view3 other projects, 6.4 GW still to connect at this substation in total. 240 MW is due to connect here before this project’s connection date of 31 Oct 2034.