NatPower Llanteg Green Energy Park
NP SPV 30 LIMITED at South Wales West Connection Node C 400kV
- Connection date
- 31 Dec 2037 +110 months since 9 Dec
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 47.5 MW
- Connected now
- 0 MW
- Still to connect
- 47.5 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004806
- In the register since
- December 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerConnection date moved from 31 Oct 2028 to 31 Dec 2037 (+110 months)
- 27 Feb 2026 registerConnection point changed from Llanteg 400kV Substation to South Wales West Connection Node C 400kV
- 27 Feb 2026 registerMarked as Gate 1
- 24 Dec 2024 registerAdded to the register
Also at South Wales West Connection Node C 400kV
Substation view1 other project, 288 MW still to connect at this substation in total.