Shotwick BESS
Shotwick Land Limited at MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
- Connection date
- 30 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 350 MW
- Connected now
- 0 MW
- Still to connect
- 350 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-003515
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 12 Jun 2026 registerSubstation name updated in the register (from Merseyside Connection Node A to MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION)
- 12 Jun 2026 registerMarked as Gate 1
- 29 Jul 2025 registerConnection point changed from Capenhurst 400kV Substation to Merseyside Connection Node A
- 26 Mar 2024 registerAdded to the register
Also at MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
Substation view1 other project, 1.3 GW still to connect at this substation in total.