Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Merthyr Solar and Battery

EEW RENEWABLES LTD at Cilfynydd 400kV Substation

Connection date
12 May 2029
Gate
Gate 1
Status
Scoping
Technology
Solar
Total capacity
175 MW
Connected now
0 MW
Still to connect
175 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002757
In the register since
May 2024

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1011011012 May 2029Gate 1Scoping
206517531 Oct 2037Gate 1Scoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 20 Oct 2026 register
    Stage 1: Marked as Gate 1
  • 20 Oct 2026 register
    Stage 2: Marked as Gate 1
  • 20 Mar 2026 register
    Customer changed from E.E.W. ECO ENERGY WORLD DEVELOPMENT HOLDING LIMITED to EEW RENEWABLES LTD
  • 28 Feb 2025 register
    Stage 2: Capacity changed from 110 MW to 65 MW
  • 28 Jun 2024 register
    New stage added (110 MW from 31 Oct 2037)
  • 31 May 2024 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO