Cilfynydd BESS
- Connection date
- 15 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 350 MW
- Connected now
- 0 MW
- Still to connect
- 350 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002756
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerConnection date moved from 15 Sep 2037 to 15 Oct 2037 (+1 month)
- 10 Oct 2026 registerConnection date moved from 15 Oct 2037 to 15 Sep 2037 (−1 month)
- 16 Dec 2025 registerMarked as Gate 1
- 27 Feb 2024 registerConnection date moved from 15 Sep 2037 to 15 Oct 2037 (+1 month)
- 30 Jun 2023 registerAdded to the register
Also at Cilfynydd 400kV Substation
Substation view8 other projects, 3 GW still to connect at this substation in total. 2.3 GW is due to connect here before this project’s connection date of 15 Oct 2037.
- Cilfynydd Grid Stability ServicesCILFYNYDD GRID SERVICES LIMITED, Other, Gate 2Mar 20270 MW
- Twyn Hywel CillfynyddTwyn Hywel Energy Park Ltd, Onshore wind, Not statedApr 2027108 MW
- Merthyr Solar and BatteryEEW RENEWABLES LTD, Solar, Gate 1May 2029175 MW
- BESS CilfynyddREWE 2 LIMITED, Storage, Not statedJul 2029200 MW
- Cilfynydd Green Energy CentreCILFYNYDD NG LIMITED, Storage with solar or wind, Gate 1Oct 20291 GW
- CilfynyddENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Oct 2030400 MW
- Penrhiwdarren FarmQAIR RENEWABLES UK LIMITED, Storage, Gate 1Sep 2037500 MW
- Cilfynydd 2REWE 8 LIMITED, Storage, Not statedOct 2037240 MW