QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Transmission / Projects / England and Wales

Oakview Farm BESS

P3P PARTNERS LLP at Hams Hall 400kV Substation

Connection date
Left 28 Mar 2025
Gate
Not stated
Status
Scoping
Technology
Storage
Total capacity
400 MW
Connected now
0 MW
Still to connect
400 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-002702
In the register since
August 2023

Change history

Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.

  • 28 Mar 2025 register
    Left the register (400 MW from 31 Oct 2033)
  • 24 Dec 2024 register
    Connection point changed from Oakview 400kV Substation to Hams Hall 400kV Substation
  • 28 Jun 2024 register
    Connection point changed from Hams Hall 400kV Substation to Oakview 400kV Substation
  • 29 Aug 2023 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO