Projects / England and Wales
Connection date
30 Oct 2026
Gate
Not stated
Status
Consented
Technology
Storage
Total capacity
400 MW
Connected now
0 MW
Still to connect
400 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001735
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10349.9349.930 Oct 2026Not statedConsented
2050399.931 Oct 2032Not statedConsented

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at Hams Hall 400kV Substation

Substation view

1 other project, 1.4 GW still to connect at this substation in total.