WELBAR ENERGY STORAGE
- Connection date
- 31 Oct 2032
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 400 MW
- Connected now
- 350 MW
- Still to connect
- 50 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001735
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 349.9 | 0 | 349.9 | None | Gate 2 | Built |
| 2 | 0 | 50 | 399.9 | 31 Oct 2032 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerStage 1: 350 MW now connected
- 27 Oct 2026 registerStage 1: Status changed from Consents Approved to Built
- 22 Oct 2026 registerStage 1: Given a Gate 2 connection offer
- 28 Feb 2023 registerRestructured from 1 stage (350 MW from 30 Oct 2026) to 2 stages (350 MW from 30 Oct 2026, 50 MW from 31 Oct 2032)
- 23 Dec 2022 registerSubstation name updated in the register (from Hams Hall/Leamarston to Hams Hall/Leamarston GSP)
- 31 Dec 2021 registerAdded to the register
Also at Hams Hall 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 31 Oct 2032.