Kirk Hill
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Planning consent
- Granted on appeal 16 Feb 2017
South Ayrshire, reference 14/01646/APPM · Source: REPD - Contract for Difference
- Allocation Round 6
- Technology
- Onshore wind
- Total capacity
- 20 MW
- Connected now
- 20 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-000320
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 May 2024 register20 MW now connected
- 31 May 2024 registerStatus changed from Consents Approved to Built
- 28 Jul 2023 registerConnection date moved from 1 May 2023 to 15 Dec 2023 (+7 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Maybole to Maybole GSP)
- 29 Jul 2022 registerConnection date moved from 31 Oct 2022 to 1 May 2023 (+6 months)
- 29 Apr 2022 registerStatus changed from Under Construction/Commissioning to Consents Approved
Also at Maybole GSP
Substation view2 other projects, 213 MW still to connect at this substation in total.