EcoMablethorpe
Econergy International Limited at Mablethorpe 400kV Substation
- Connection date
- 30 Aug 2034
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 249 MW
- Connected now
- 0 MW
- Still to connect
- 249 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002583
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 17 Apr 2026 registerMarked as Gate 1
- 30 Jun 2023 registerAdded to the register
Also at Mablethorpe 400kV Substation
Substation view1 other project, 1.3 GW still to connect at this substation in total. 1 GW is due to connect here before this project’s connection date of 30 Aug 2034.