BESS North Farm
- Connection date
- 1 Nov 2031
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 0 MW
- Still to connect
- 150 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-002060
- In the register since
- June 2023
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 22 May 2026 registerMarked as Gate 1
- 30 Jul 2024 registerCustomer changed from CSWE 5 LIMITED to REWE 5 LIMITED
- 30 Jun 2023 registerAdded to the register
Also at Chickerell 400kV Substation
Substation view4 other projects, 3.5 GW still to connect at this substation in total. 400 MW is due to connect here before this project’s connection date of 1 Nov 2031.
- Chickerell Solar PV & BESSCHICKERELL STORAGE LIMITED, Storage, Gate 2Oct 2028400 MW
- ChickerellENSO GREEN HOLDINGS X LIMITED, Storage with solar or wind, Gate 1Dec 2036400 MW
- PortwindSE PORTWIND LTD, Offshore wind, Gate 1Dec 20362.5 GW
- ChickerellSSE GENERATION LIMITED, Thermal (gas, biomass, waste), Not statedConnected47 MW