Dungeness Energy Park
SOUTH KENT ENERGY PARK LIMITED at Dungeness 400kV Substation
- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001986
- In the register since
- June 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 21 Apr 2026 registerMarked as Gate 1
- 13 Mar 2026 registerConnection point changed from East Kent connection node A 400kV Substation to Dungeness 400kV Substation
- 31 Jan 2025 registerCustomer changed from LOW CARBON SOLAR PARK 14 LIMITED to SOUTH KENT ENERGY PARK LIMITED
- 30 Jul 2024 registerRestructured from 2 stages (500 MW from 31 Dec 2030, 0 MW from 31 Dec 2037) to 1 stage (500 MW from 31 Oct 2037). First connection date +82 months
- 28 Jun 2024 registerRestructured from 1 stage (500 MW from 31 Oct 2031) to 2 stages (500 MW from 31 Dec 2030, 0 MW from 31 Dec 2037). First connection date −10 months
- 28 Nov 2023 registerConnection point changed from Dungeness 400kV Substation to Newchurch 400kV Substation
- 28 Nov 2023 registerConnection date moved from 1 Apr 2029 to 31 Oct 2031 (+31 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Dungeness 400KV to Dungeness 400kV Substation)
- 30 Jun 2022 registerAdded to the register
Also at Dungeness 400kV Substation
Substation view1 other project, 1 GW still to connect at this substation in total. 500 MW is due to connect here before this project’s connection date of 31 Oct 2037.