BLUE PLANET SOLAR
- Connection date
- 31 Aug 2031
- Gate
- Not stated
- Status
- Scoping
- Technology
- Storage + Solar
- Total capacity
- 500 MW
- Connected now
- 0 MW
- Still to connect
- 500 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001703
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 May 2025 registerConnection date moved from 31 Oct 2029 to 31 Aug 2031 (+22 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Dungeness 400KV to Dungeness 400kV Substation)
- 31 Dec 2021 registerAdded to the register
Also at Dungeness 400kV Substation
Substation view1 other project, 1 GW still to connect at this substation in total.