Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Margree Wind Farm

ENERGYFARM UK MARGREE LLP at SPT Margree collector substation

Connection date
31 Oct 2029
Gate
Not stated
Status
Awaiting Consents
Technology
Onshore wind
Total capacity
50 MW
Connected now
0 MW
Still to connect
50 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001789
In the register since
January 2022

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Apr 2025 register
    Connection point changed from Quantans Hill 132kV to SPT Margree collector substation
  • 29 Apr 2025 register
    Connection date moved from 31 Oct 2027 to 31 Oct 2029 (+24 months)
  • 31 Mar 2023 register
    Connection point changed from Glenshimmeroch 132kV Substation to Quantans Hill 132kV
  • 31 Mar 2023 register
    Connection date moved from 26 Aug 2027 to 31 Oct 2027 (+2 months)
  • 31 Jan 2023 register
    Connection date moved from 12 May 2026 to 26 Aug 2027 (+15 months)
  • 23 Dec 2022 register
    Substation name updated in the register (from Glenshimmeroch 132kV to Glenshimmeroch 132kV Substation)
  • 28 Jan 2022 register
    Added to the register

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO