Glenshimmeroch Windfarm
ENERGYFARM UK GLENSHIMMEROCH LLP at SPT Margree collector substation
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 45 MW
- Connected now
- 0 MW
- Still to connect
- 45 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000440
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Apr 2025 registerConnection date moved from 31 Oct 2027 to 31 Oct 2029 (+24 months)
- 29 Oct 2024 registerConnection point changed from Quantans Hill 132kV to SPT Margree collector substation
- 29 Oct 2024 registerCapacity changed from 50 MW to 45 MW
- 29 Oct 2024 registerConnection date moved from 26 Aug 2027 to 31 Oct 2027 (+2 months)
- 31 Mar 2023 registerConnection point changed from Glenshimmeroch 132kV Substation to Quantans Hill 132kV
- 31 Jan 2023 registerConnection date moved from 5 Aug 2026 to 26 Aug 2027 (+13 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Glenshimmeroch 132kV to Glenshimmeroch 132kV Substation)
- 30 Jun 2022 registerStage removed (37 MW from 31 Jul 2025)
- 30 Jun 2022 registerStage removed (11 MW from 30 Sep 2025)
- 31 May 2022 registerNew stage added (50 MW from 5 Aug 2026)
- 31 Dec 2021 registerRestructured from 1 stage (48 MW from 31 Jul 2025) to 2 stages (37 MW from 31 Jul 2025, 11 MW from 30 Sep 2025)
- 30 Apr 2021 registerConnection date moved from 31 Oct 2023 to 31 Jul 2025 (+21 months)
- 30 Apr 2021 registerStatus changed from Awaiting Consents to Consents Approved
Also at SPT Margree collector substation
Substation view2 other projects, 145 MW still to connect at this substation in total.