Fell Wind Farm
- Connection date
- 31 Oct 2029
- Gate
- Not stated
- Status
- Scoping
- Planning consent
- Granted on appeal 2 Nov 2021
Dumfries and Galloway, reference 20/0148/FUL · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 50 MW
- Connected now
- 0 MW
- Still to connect
- 50 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001755
- In the register since
- February 2022
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Apr 2025 registerConnection point changed from Fell Wind Farm 132/33kV Substation to SPT Margree collector substation
- 29 Apr 2025 registerConnection date moved from 31 Oct 2027 to 31 Oct 2029 (+24 months)
- 26 Nov 2024 registerConnection date moved from 30 Oct 2028 to 31 Oct 2027 (−12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Fell Wind Farm 132/33kV to Fell Wind Farm 132/33kV Substation)
- 25 Feb 2022 registerAdded to the register
Also at SPT Margree collector substation
Substation view2 other projects, 145 MW still to connect at this substation in total.