- Connection date
- 1 Jun 2029
- Gate
- Not stated
- Status
- Awaiting Consents
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001537
- In the register since
- May 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Jan 2026 registerConnection point changed from Norton 400kV Substation to Norton 275kV Substation
- 21 Nov 2025 registerConnection date moved from 1 May 2025 to 1 Jun 2029 (+49 months)
- 29 Apr 2025 registerTechnology changed from Storage, Solar to Storage
- 30 Mar 2022 registerSubstation name updated in the register (from Norton to Norton 400kV Substation)
- 29 Jun 2021 registerStatus changed from Scoping to Awaiting Consents
- 28 May 2021 registerAdded to the register
Also at Norton 275kV Substation
Substation view1 other project, 97.9 MW still to connect at this substation in total. 40.9 MW is due to connect here before this project’s connection date of 1 Jun 2029.