Norton PV and BESS
- Connection date
- 31 Oct 2027
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 40.9 MW
- Connected now
- 0 MW
- Still to connect
- 40.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001437
- In the register since
- December 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 16 Oct 2026 registerGiven a Gate 2 connection offer
- 4 Aug 2026 registerConnection point changed from Norton 400kV Substation to Norton 275kV Substation
- 19 Dec 2025 registerConnection point changed from Norton 275kV Substation to Norton 400kV Substation
- 29 Apr 2025 registerConnection date moved from 31 Oct 2024 to 31 Oct 2027 (+36 months)
- 31 Jan 2025 registerConnection point changed from Norton 400kV Substation to Norton 275kV Substation
- 28 Jul 2023 registerCustomer changed from CS UK HOLDINGS III LIMITED to Darlington Solar 1 Limited
- 30 Jun 2023 registerConnection date moved from 31 Jul 2023 to 31 Oct 2024 (+15 months)
- 30 May 2023 registerStatus changed from Scoping to Consents Approved
- 30 Mar 2022 registerSubstation name updated in the register (from Norton to Norton 400kV Substation)
- 31 Dec 2021 registerAdded to the register
Also at Norton 275kV Substation
Substation view1 other project, 97.9 MW still to connect at this substation in total.