- Connection date
- 31 Oct 2037
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Solar + Onshore wind
- Total capacity
- 297 MW
- Connected now
- 0 MW
- Still to connect
- 297 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004798
- In the register since
- January 2025
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 25 Aug 2026 registerConnection point changed from Oswestry Substation to MID WALES CONNECTION NODE A 400KV SUBSTATION
- 25 Aug 2026 registerMarked as Gate 1
- 31 Jan 2025 registerAdded to the register
Also at MID WALES CONNECTION NODE A 400KV SUBSTATION
Substation view3 other projects, 799 MW still to connect at this substation in total. 100 MW is due to connect here before this project’s connection date of 31 Oct 2037.
- Mynydd Y GwyntEDF ENERGY RENEWABLES LIMITED, Storage with solar or wind, Not statedOct 2037100 MW
- Garn Fach Wind FarmEDF ENERGY RENEWABLES LIMITED, Storage with solar or wind, Not statedOct 2037162 MW
- Lightsource BerthlwydLightsource Renewable UK Development Limited, Storage with solar or wind, Gate 1Oct 2037240 MW