Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Menter Mon Morlais Anglesey Marine Energy

Menter Môn Morlais Limited at Penrhos GSP

Connection date
31 Mar 2028
Gate
Not stated
Status
Under Construction/Commissioning
Technology
Tidal
Total capacity
180 MW
Connected now
0 MW
Still to connect
180 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001134
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
10404031 Mar 2028Not statedUnder Construction/Commissioning
20206031 Mar 2029Not statedUnder Construction/Commissioning
304010031 Mar 2030Not statedUnder Construction/Commissioning
408018031 Mar 2032Not statedUnder Construction/Commissioning

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 30 May 2025 register
    Stage 1: Status changed from Scoping to Under Construction/Commissioning
  • 30 May 2025 register
    Stage 2: Status changed from Scoping to Under Construction/Commissioning
  • 30 May 2025 register
    Stage 3: Status changed from Scoping to Under Construction/Commissioning
  • 30 May 2025 register
    Stage 4: Status changed from Scoping to Under Construction/Commissioning
  • 26 Nov 2024 register
    Customer changed from Menter Mon Morlais Limited to MENTER MÔN MORLAIS LIMITED
  • 31 May 2024 register
    Customer changed from MENTER MON CYF to Menter Mon Morlais Limited
  • 26 Apr 2024 register
    Stage 2: Connection date moved from 1 Apr 2029 to 31 Mar 2029 (1 day earlier)
  • 26 Apr 2024 register
    Stage 3: Connection date moved from 1 Apr 2030 to 31 Mar 2030 (1 day earlier)
  • 26 Apr 2024 register
    Stage 4: Connection date moved from 1 Apr 2032 to 31 Mar 2032 (1 day earlier)
  • 28 Jul 2023 register
    Renamed from Morlais
  • 28 Jul 2023 register
    Stage 1: Connection date moved from 1 Apr 2028 to 31 Mar 2028 (1 day earlier)
  • 23 Dec 2022 register
    Substation name updated in the register (from Penrhos to Penrhos GSP)
  • 26 Feb 2021 register
    Stage 1: Connection date moved from 4 Jan 2028 to 1 Apr 2028 (+3 months)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 4 Jan 2029 to 1 Apr 2029 (+3 months)
  • 26 Feb 2021 register
    Stage 3: Connection date moved from 4 Jan 2030 to 1 Apr 2030 (+3 months)
  • 26 Feb 2021 register
    Stage 4: Connection date moved from 4 Jan 2032 to 1 Apr 2032 (+3 months)

Also at Penrhos GSP

Substation view

1 other project, 390 MW still to connect at this substation in total. 210 MW is due to connect here before this project’s connection date of 31 Mar 2028.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO