Projects / England and Wales
Connection date
30 Oct 2025
Gate
Not stated
Status
Consented
Technology
Biomass
Total capacity
210 MW
Connected now
0 MW
Still to connect
210 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-000330
Tracked since
14 Aug 2026

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1015015030 Oct 2025Not statedConsented
206021031 Oct 2027Not statedConsented

Change history

Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.

No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.

Also queued at Penrhos GSP

Substation view

1 other project, 390 MW still to connect at this substation in total.