Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Recell at Penrhos (BEGA)

Recell Energy Bloom Developments Limited at Penrhos GSP

Connection date
30 Oct 2025
Gate
Not stated
Status
Consents Approved
Technology
Biomass
Total capacity
210 MW
Connected now
0 MW
Still to connect
210 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Embedded
Region
England and Wales
Project number
PRO-000330
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
1015015030 Oct 2025Not statedConsents Approved
206021031 Oct 2027Not statedConsents Approved

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 3 Jul 2026 register
    Stage 2: Connection date moved from 30 Jun 2026 to 31 Oct 2027 (+16 months)
  • 6 Mar 2026 register
    Stage 2: Connection date moved from 31 Oct 2027 to 30 Jun 2026 (−16 months)
  • 3 Mar 2026 register
    Stage 2: Connection date moved from 30 Jun 2026 to 31 Oct 2027 (+16 months)
  • 21 Nov 2025 register
    Stage 2: Connection date moved from 8 Mar 2027 to 30 Jun 2026 (−8 months)
  • 24 Dec 2024 register
    Stage 2: Connection date moved from 31 Oct 2027 to 8 Mar 2027 (−8 months)
  • 26 Mar 2024 register
    Renamed from Holyhead
  • 31 Jan 2023 register
    Customer changed from ORTHIOS POWER (ANGLESEY) LIMITED to Recell Energy Bloom Developments Limited
  • 23 Dec 2022 register
    Customer changed from Recell Energy Bloom Developments Limited to ORTHIOS POWER (ANGLESEY) LIMITED
  • 23 Dec 2022 register
    Substation name updated in the register (from Penrhos to Penrhos GSP)
  • 29 Nov 2022 register
    Customer changed from ORTHIOS POWER (ANGLESEY) LIMITED to Recell Energy Bloom Developments Limited
  • 29 Nov 2022 register
    Stage 1: Connection date moved from 30 Oct 2021 to 30 Oct 2025 (+48 months)
  • 29 Nov 2022 register
    Stage 2: Connection date moved from 1 Apr 2023 to 31 Oct 2027 (+55 months)
  • 25 Feb 2022 register
    Stage 1: Connection date moved from 31 Oct 2021 to 30 Oct 2021 (1 day earlier)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)

Also at Penrhos GSP

Substation view

1 other project, 390 MW still to connect at this substation in total.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO