Menter Môn Morlais Limited
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Menter Mon Morlais Anglesey Marine Energy | Penrhos GSP | Hydro & marine | 180 | 31 Mar 2028 | Not stated | Under Construction/Commissioning |
Recent changes
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 1: Status changed from Scoping to Under Construction/Commissioning
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 2: Status changed from Scoping to Under Construction/Commissioning
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 3: Status changed from Scoping to Under Construction/Commissioning
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 4: Status changed from Scoping to Under Construction/Commissioning
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineCustomer changed from Menter Mon Morlais Limited to MENTER MÔN MORLAIS LIMITED
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineCustomer changed from MENTER MON CYF to Menter Mon Morlais Limited
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 2: Connection date moved from 1 Apr 2029 to 31 Mar 2029 (1 day earlier)
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 3: Connection date moved from 1 Apr 2030 to 31 Mar 2030 (1 day earlier)
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 4: Connection date moved from 1 Apr 2032 to 31 Mar 2032 (1 day earlier)
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineRenamed from Morlais
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 1: Connection date moved from 1 Apr 2028 to 31 Mar 2028 (1 day earlier)
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineSubstation name updated in the register (from Penrhos to Penrhos GSP)
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 1: Connection date moved from 4 Jan 2028 to 1 Apr 2028 (+3 months)+3 mo
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 2: Connection date moved from 4 Jan 2029 to 1 Apr 2029 (+3 months)+3 mo
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 3: Connection date moved from 4 Jan 2030 to 1 Apr 2030 (+3 months)+3 mo
- Menter Mon Morlais Anglesey Marine EnergyEngland and Wales, Hydro & marineStage 4: Connection date moved from 4 Jan 2032 to 1 Apr 2032 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?