West Weybridge
EL (WEST WEYBRIDGE) LIMITED at West Weybridge 275kV Substation
- Connection date
- 30 Sep 2028 +11 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 57 MW
- Connected now
- 0 MW
- Still to connect
- 57 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-004324
- In the register since
- March 2024
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 1 Oct 2026 registerConnection date moved from 31 Oct 2027 to 30 Sep 2028 (+11 months)
- 1 Oct 2026 registerGiven a Gate 2 connection offer
- 26 Nov 2024 registerStatus changed from Scoping to Consents Approved
- 26 Mar 2024 registerAdded to the register
Also at West Weybridge 275kV Substation
Substation viewNo other projects in the register at this connection point.