Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Berkswell (Tertiary)

ENSO GREEN HOLDINGS P LIMITED at Berkswell 275kV Substation

Connection date
30 May 2028
Gate
Not stated
Status
Consents Approved
Technology
Storage + Solar
Total capacity
57 MW
Connected now
0 MW
Still to connect
57 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000516
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 27 Jun 2025 register
    Customer changed from ENSO GREEN HOLDINGS LIMITED to ENSO Green Holdings P Limited
  • 27 Jun 2025 register
    Status changed from Scoping to Consents Approved
  • 27 Jun 2025 register
    Stage removed (49.9 MW from 31 Oct 2025)
  • 27 Jun 2025 register
    Stage removed (7.1 MW from 31 Oct 2027)
  • 30 May 2025 register
    New stage added (57 MW from 30 May 2028)
  • 31 May 2022 register
    Stage 1: Technology changed from Hybrid to Storage, Solar
  • 31 May 2022 register
    Stage 2: Technology changed from Hybrid to Storage, Solar
  • 30 Mar 2022 register
    Substation name updated in the register (from Berkswell to Berkswell 275kV Substation)
  • 30 Mar 2022 register
    Stage 1: Technology changed from Storage, Solar to Hybrid
  • 30 Mar 2022 register
    Stage 2: Technology changed from Storage, Solar to Hybrid

Also at Berkswell 275kV Substation

Substation view

1 other project, 257 MW still to connect at this substation in total. 200 MW is due to connect here before this project’s connection date of 30 May 2028.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO