ENSO GREEN HOLDINGS P LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Berkswell (Tertiary) | Berkswell 275kV Substation | Storage with solar or wind | 57 | 30 May 2028 | Not stated | Consents Approved |
Recent changes
- Berkswell (Tertiary)England and Wales, Storage with solar or windCustomer changed from ENSO GREEN HOLDINGS LIMITED to ENSO Green Holdings P Limited
- Berkswell (Tertiary)England and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage removed (49.9 MW from 31 Oct 2025)
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage removed (7.1 MW from 31 Oct 2027)
- Berkswell (Tertiary)England and Wales, Storage with solar or windNew stage added (57 MW from 30 May 2028)
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage 1: Technology changed from Hybrid to Storage, Solar
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage 2: Technology changed from Hybrid to Storage, Solar
- Berkswell (Tertiary)England and Wales, Storage with solar or windSubstation name updated in the register (from Berkswell to Berkswell 275kV Substation)
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage 1: Technology changed from Storage, Solar to Hybrid
- Berkswell (Tertiary)England and Wales, Storage with solar or windStage 2: Technology changed from Storage, Solar to Hybrid
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?