Berkswell Energy Storage
BERKSWELL BATTERY STORAGE LIMITED at Berkswell 275kV Substation
- Connection date
- 31 Oct 2027 +6 months since 9 Dec
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001788
- In the register since
- February 2022
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 24 Jul 2026 registerConnection date moved from 30 Apr 2027 to 31 Oct 2027 (+6 months)
- 14 Jul 2026 registerGiven a Gate 2 connection offer
- 29 Aug 2025 registerCustomer changed from BW ESS Development UK Limited to Berkswell Battery Storage Limited
- 27 Jun 2025 registerConnection date moved from 31 Oct 2026 to 30 Apr 2027 (+6 months)
- 27 Jun 2025 registerStatus changed from Awaiting Consents to Consents Approved
- 31 Jan 2025 registerCustomer changed from Penso Power Limited to BW ESS DEVELOPMENT UK LIMITED
- 30 Mar 2022 registerSubstation name updated in the register (from Berkswell to Berkswell 275kV Substation)
- 25 Feb 2022 registerAdded to the register
Also at Berkswell 275kV Substation
Substation view1 other project, 257 MW still to connect at this substation in total.