Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

SSE Renewables Services (UK) Limited

Customer named in the TEC register

4projects in the register
404 MWstill to connect
0 MWof that with Gate 2 offers
0 MWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
Tangy IV WFTangy IV 132KV SubstationOnshore wind9630 Apr 2029Not statedScoping
Fairburn Extension Wind FarmFairburn Extension 132/33kV SubstationOnshore wind9031 Oct 2031Gate 1Scoping
Glentarken Wind FarmGLENTARKEN WIND FARM 132/33KV SUBSTATIONOnshore wind10430 Nov 2031Gate 1Scoping
Brown Rig Wind FarmHawick 132kV SubstationOnshore wind11431 Oct 2033Gate 1Scoping

Left the register since January 2021: Glencassley Wind Farm (65 MW), Tangy III Wind Farm (39.1 MW).

Recent changes

  • Fairburn Extension Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • Glentarken Wind FarmNorth Scotland, Onshore windConnection point changed from Killin GSP to GLENTARKEN WIND FARM 132/33KV SUBSTATION
  • Glentarken Wind FarmNorth Scotland, Onshore windMarked as Gate 1
  • Brown Rig Wind FarmSouth Scotland, Onshore windMarked as Gate 1
  • Tangy IV WFNorth Scotland, Onshore windConnection date moved from 31 Oct 2026 to 30 Apr 2029 (+30 months)+30 mo
  • Tangy IV WFNorth Scotland, Onshore windTechnology changed from Onshore wind to Onshore wind, Substation
  • Fairburn Extension Wind FarmNorth Scotland, Onshore windAdded to the registerNew
  • Glencassley Wind FarmNorth Scotland, Onshore windLeft the register (65 MW from 31 Oct 2026)65 MW
  • Glentarken Wind FarmNorth Scotland, Onshore windAdded to the registerNew
  • Brown Rig Wind FarmSouth Scotland, Onshore windAdded to the registerNew
  • Glencassley Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP to Shin GSP)
  • Glencassley Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2025 to 31 Oct 2026 (+19 months)+19 mo
  • Glencassley Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Shin 132/33kV GSP Substation to Shin 132/33kV GSP)
  • Tangy III Wind FarmNorth Scotland, Onshore windLeft the register (39.1 MW from 1 Apr 2025)39.1 MW
  • Glencassley Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2024 to 1 Apr 2025 (+11 months)+11 mo
  • Tangy III Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Carradale to Carradale GSP)
  • Tangy III Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2023 to 1 Apr 2025 (+24 months)+24 mo
  • Tangy IV WFNorth Scotland, Onshore windAdded to the registerNew
  • Tangy III Wind FarmNorth Scotland, Onshore windConnection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO