Projects / England and Wales
- Connection date
- 1 Jul 2027
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Gas engines
- Total capacity
- 1,318 MW
- Connected now
- 1,268 MW
- Still to connect
- 50 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000053
- Tracked since
- 14 Aug 2026
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| Unnumbered | 0 | 50 | 1,318 | 1 Jul 2027 | Gate 1 | Scoping |
| Unnumbered | 1,268 | 0 | 1,268 | None | Not stated | Built |
Change history
Every change to this project across 9 registers from 14 Aug 2026 to 21 Sep 2026.
No changes since 14 Aug 2026. Follow this project to see the next one on your watchlist.
Also queued at Humber Refinery 400kV Substation
Substation view1 other project, 349 MW still to connect at this substation in total.