QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
31 Oct 2028
Gate
Gate 1
Status
Scoping
Technology
Storage + Gas engines
Total capacity
1,318 MW
Connected now
1,268 MW
Still to connect
50 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-000053
In the register since
January 2021 or earlier

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
11,26801,268NoneNot statedBuilt
20501,31831 Oct 2028Gate 1Scoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 16 Oct 2026 register
    Stage 2: Connection date moved from 1 Jul 2027 to 31 Oct 2028 (+16 months)
  • 16 Oct 2026 register
    1,268 MW connected moved from stage 2 to stage 1 in the register (connected MW unchanged)
  • 10 Oct 2026 register
    Restructured from 2 stages (50 MW from 1 Jul 2027, 1,268 MW connected) to 2 stages (1,268 MW connected + 50 MW from 1 Jul 2027, 1,268 MW)
  • 10 Jul 2026 register
    Marked as Gate 1
  • 21 Nov 2025 register
    Customer changed from VPI Power Limited to VPI IMMINGHAM LLP
  • 21 Nov 2025 register
    Stage removed (50 MW from 31 Oct 2029)
  • 31 Oct 2025 register
    50 MW now connected
  • 31 Oct 2025 register
    Capacity changed from 1,218 MW to 1,268 MW
  • 29 Jul 2025 register
    Customer changed from VPI IMMINGHAM LLP to VPI Power Limited
  • 31 Jan 2025 register
    Capacity changed from 50 MW to 0 MW
  • 31 Jan 2025 register
    Connection date removed (was 29 Sep 2023)
  • 31 Jan 2025 register
    Technology changed from CHP, Storage to Storage, Gas engines
  • 31 Jan 2025 register
    New stage added (50 MW from 1 Jul 2027)
  • 31 Jan 2025 register
    New stage added (50 MW from 31 Oct 2029)
  • 30 Jan 2024 register
    Technology changed from CHP to CHP, Storage
  • 29 Sep 2023 register
    Connection date set to 29 Sep 2023
  • 29 Aug 2023 register
    Restructured from 3 stages (50 MW from 1 Oct 2022, 1,218 MW connected + 50 MW from 30 May 2025, 1,218 MW connected) to 1 stage (1,218 MW connected + 50 MW)
  • 28 Jul 2023 register
    New stage added (1,218 MW connected + 50 MW from 30 May 2025)
  • 23 Dec 2022 register
    Substation name updated in the register (from Humber Refinery 400kV to Humber Refinery 400kV Substation)
  • 30 Mar 2021 register
    Stage 2: Connection date moved from 1 Oct 2020 to 1 Oct 2022 (+24 months)
  • 26 Feb 2021 register
    Stage 2: Connection date moved from 10 Jan 2020 to 1 Oct 2020 (+9 months)

Also at Humber Refinery 400kV Substation

Substation view

1 other project, 349 MW still to connect at this substation in total. 299 MW is due to connect here before this project’s connection date of 31 Oct 2028.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO