Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

VPI IMMINGHAM LLP

Customer named in the TEC register

1project in the register
50 MWstill to connect
0 MWof that with Gate 2 offers
1.3 GWconnected now

Projects

ProjectConnection siteTechnologyQueued MWConnection dateGateStatus
ImminghamHumber Refinery 400kV SubstationThermal (gas, biomass, waste)5031 Oct 2028Gate 1Scoping

Recent changes

  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 1 Jul 2027 to 31 Oct 2028 (+16 months)+16 mo
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)1,268 MW connected moved from stage 2 to stage 1 in the register (connected MW unchanged)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Restructured from 2 stages (50 MW from 1 Jul 2027, 1,268 MW connected) to 2 stages (1,268 MW connected + 50 MW from 1 Jul 2027, 1,268 MW)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Customer changed from VPI Power Limited to VPI IMMINGHAM LLP
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage removed (50 MW from 31 Oct 2029)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)50 MW now connectedConnected
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 1,218 MW to 1,268 MW
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Customer changed from VPI IMMINGHAM LLP to VPI Power Limited
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 50 MW to 0 MW
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Connection date removed (was 29 Sep 2023)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Technology changed from CHP, Storage to Storage, Gas engines
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (50 MW from 1 Jul 2027)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (50 MW from 31 Oct 2029)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Technology changed from CHP to CHP, Storage
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 29 Sep 2023
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Restructured from 3 stages (50 MW from 1 Oct 2022, 1,218 MW connected + 50 MW from 30 May 2025, 1,218 MW connected) to 1 stage (1,218 MW connected + 50 MW)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (1,218 MW connected + 50 MW from 30 May 2025)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Humber Refinery 400kV to Humber Refinery 400kV Substation)
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 1 Oct 2020 to 1 Oct 2022 (+24 months)+24 mo
  • ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 10 Jan 2020 to 1 Oct 2020 (+9 months)+9 mo
QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my projectSee use cases

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO