VPI IMMINGHAM LLP
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Immingham | Humber Refinery 400kV Substation | Thermal (gas, biomass, waste) | 50 | 31 Oct 2028 | Gate 1 | Scoping |
Recent changes
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 1 Jul 2027 to 31 Oct 2028 (+16 months)+16 mo
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)1,268 MW connected moved from stage 2 to stage 1 in the register (connected MW unchanged)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Restructured from 2 stages (50 MW from 1 Jul 2027, 1,268 MW connected) to 2 stages (1,268 MW connected + 50 MW from 1 Jul 2027, 1,268 MW)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Marked as Gate 1
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Customer changed from VPI Power Limited to VPI IMMINGHAM LLP
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage removed (50 MW from 31 Oct 2029)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)50 MW now connectedConnected
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 1,218 MW to 1,268 MW
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Customer changed from VPI IMMINGHAM LLP to VPI Power Limited
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Capacity changed from 50 MW to 0 MW
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Connection date removed (was 29 Sep 2023)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Technology changed from CHP, Storage to Storage, Gas engines
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (50 MW from 1 Jul 2027)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (50 MW from 31 Oct 2029)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Technology changed from CHP to CHP, Storage
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Connection date set to 29 Sep 2023
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Restructured from 3 stages (50 MW from 1 Oct 2022, 1,218 MW connected + 50 MW from 30 May 2025, 1,218 MW connected) to 1 stage (1,218 MW connected + 50 MW)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)New stage added (1,218 MW connected + 50 MW from 30 May 2025)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Humber Refinery 400kV to Humber Refinery 400kV Substation)
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 1 Oct 2020 to 1 Oct 2022 (+24 months)+24 mo
- ImminghamEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 10 Jan 2020 to 1 Oct 2020 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?